Samples: Implementation Timeline & RFP
Two templates to adapt for your own project: a 12-month TMS implementation timeline broken into six phases, and the table of contents for a TMS request for proposal (RFP).
Sample 1 of 2
Sample Implementation Timeline
Twelve months from kickoff to optimization. Treat the durations as a starting point: scope, entity count and integrations move them.
- Phase 01
Planning and Preparation
Months 1–2Project kickoffRequirements gatheringCurrent state assessmentVendor selection (if applicable)Project team formationStakeholder engagementInitial planningInfrastructure assessmentRisk assessmentCommunication plan development - Phase 02
Design and Configuration
Months 3–4Detailed design workshopsConfiguration specificationsIntegration designReport specificationsSecurity model designControl framework designWorkflow developmentTest planningTraining needs assessmentChange impact analysis - Phase 03
Build and Test
Months 5–7System configurationIntegration developmentReport developmentSecurity implementationWorkflow configurationUser acceptance test preparationUnit testingIntegration testingData migration planningTraining material development - Phase 04
Testing and Training
Months 8–9User acceptance testingIntegration validationPerformance testingSecurity validationDisaster recovery testingEnd-user training deliveryAdministrator trainingProcess documentationCutover planningGo-live readiness assessment - Phase 05
Go-Live and Stabilization
Month 10Final data migrationProduction cutoverGo-live supportIssue resolutionPerformance monitoringUser supportProcess validationControl effectiveness verificationDocumentation finalizationKnowledge transfer - Phase 06
Optimization and Expansion
Months 11–12Post-implementation reviewPerformance optimizationFunctionality expansionAdditional integrationReport enhancementUser experience improvementProcess refinementAdditional trainingContinuous improvement planningFuture phase preparation
Sample 2 of 2
Sample RFP Table of Contents
A structure for a TMS request for proposal: 10 sections and 10 appendices, from company background to the response format vendors must follow.
- 01
Introduction
- 1.1Company Overview
- 1.2Project Background
- 1.3Purpose of RFP
- 1.4RFP Timeline
- 1.5Submission Instructions
- 1.6Evaluation Process
- 1.7Contact Information
- 02
Current Environment
- 2.1Treasury Organization
- 2.2Treasury Processes
- 2.3Technology Landscape
- 2.4Banking Structure
- 2.5Transaction Volumes
- 2.6Pain Points and Challenges
- 2.7Future State Vision
- 03
Project Scope
- 3.1Modules in Scope
- 3.2Geographic Coverage
- 3.3Entity Scope
- 3.4User Base
- 3.5Language Requirements
- 3.6Implementation Timeline
- 3.7Budget Framework
- 04
Functional Requirements
- 4.1Cash Management
- 4.2Payment Processing
- 4.3Bank Account Management
- 4.4Forecasting
- 4.5Risk Management
- 4.6Investment Management
- 4.7Debt Management
- 4.8In-house Banking
- 4.9Accounting Integration
- 4.10Reporting and Analytics
- 05
Technical Requirements
- 5.1System Architecture
- 5.2Security Requirements
- 5.3Integration Requirements
- 5.4Performance Expectations
- 5.5Availability Requirements
- 5.6Disaster Recovery
- 5.7Mobile Capabilities
- 5.8Browser Compatibility
- 5.9Customization Capabilities
- 5.10Upgrade Process
- 06
Implementation and Support
- 6.1Implementation Methodology
- 6.2Project Management Approach
- 6.3Resource Requirements
- 6.4Testing Approach
- 6.5Training Requirements
- 6.6Documentation Expectations
- 6.7Support Model
- 6.8Service Level Agreements
- 6.9User Community Access
- 6.10Enhancement Process
- 07
Vendor Information
- 7.1Company Background
- 7.2Financial Stability
- 7.3Client Base and References
- 7.4Product Roadmap
- 7.5Partnership Ecosystem
- 7.6Implementation Resources
- 7.7Support Capabilities
- 7.8Industry Recognition
- 7.9Case Studies
- 7.10Differentiation
- 08
Pricing Information
- 8.1License/Subscription Costs
- 8.2Implementation Services
- 8.3Training Costs
- 8.4Support and Maintenance
- 8.5Additional Module Pricing
- 8.6User-based Pricing Tiers
- 8.7Volume-based Considerations
- 8.8Travel Expenses
- 8.9Hardware Requirements
- 8.10Total Cost of Ownership
- 09
Evaluation Criteria
- 9.1Functional Fit
- 9.2Technical Alignment
- 9.3Implementation Approach
- 9.4Support Model
- 9.5Vendor Stability
- 9.6Cost Structure
- 9.7User Experience
- 9.8Client References
- 9.9Innovation Capability
- 9.10Strategic Partnership Potential
- 10
Response Format
- 10.1Executive Summary
- 10.2Functional Response
- 10.3Technical Response
- 10.4Implementation Approach
- 10.5Support Model
- 10.6Company Information
- 10.7Pricing Details
- 10.8Client References
- 10.9Sample Contracts
- 10.10Additional Information
Appendices
- ADetailed Functional Requirements Matrix
- BTechnical Infrastructure Diagram
- CCurrent Process Flows
- DVolume Statistics
- ESample Reports
- FKey Project Milestones
- GResponse Templates
- HEvaluation Criteria Weighting
- IContract Terms and Conditions
- JNon-Disclosure Agreement